Skip to content
No Second Trip

Concrete and Masonry Costs and Calculators

Concrete is the one material where ordering short is genuinely expensive: a slab has to be poured in one go, and a truck that leaves half a yard short leaves you with a cold joint through the middle of it. Almost every question below is really about ordering slightly more than you think you need.

Wet concrete running down a truck chute into a timber-formed slab, with reinforcing mesh visible in the unpoured section.

Calculators

Working out the volume

Concrete is sold by the cubic yard, and jobs are measured in feet and inches. The conversion is exact — 27 cubic feet to the yard — but it is also where most mistakes happen, because depth is usually in inches while length and width are in feet. Convert the depth first, or the answer comes out twelve times too large.

A four inch slab is the residential default, and it is thicker than it looks on paper: a 20 by 10 foot patio at four inches is nearly three cubic yards, about six tons of material. Anywhere a vehicle runs, five or six inches is the honest minimum, and the thickened edge around the perimeter adds more volume than people expect.

Order for the forms, not for the drawing. Sub-grade is never perfectly flat, and the low spots are real volume. Five percent over is sensible on a formed slab on a prepared base; ten is more realistic on open ground.

Volume before any waste allowance. Add five to ten percent for sub-grade variation and the thickened edge.
SlabAt 4 inAt 5 inAt 6 inWeight at 4 in
10 × 10 ft1.23 cu yd1.54 cu yd1.85 cu yd2.5 tons
12 × 12 ft1.78 cu yd2.22 cu yd2.67 cu yd3.6 tons
20 × 10 ft2.47 cu yd3.09 cu yd3.70 cu yd5.0 tons
20 × 20 ft4.94 cu yd6.17 cu yd7.41 cu yd10.0 tons
24 × 24 ft (2-car garage)7.11 cu yd8.89 cu yd10.67 cu yd14.4 tons

Bags or a ready-mix truck

The crossover is around one cubic yard, which is 45 eighty-pound bags. Below that, bags win on convenience and there is no delivery minimum to meet. Above it, the bags cost more than the concrete does, and you are mixing for hours.

The quality argument matters more than the price one. A truck delivers a single batch, mixed to a consistent water-cement ratio, placed in one pour. Forty-five bags is forty-five separate mixes, each slightly different, going off progressively as you work. For anything structural, or anything that has to look uniform, that difference shows.

Ready-mix suppliers usually have a minimum load — commonly one yard, sometimes more — and charge a short-load fee below it. Ask before you assume the truck is uneconomic, because the fee is often less than the extra bags would cost.

Yields are the mixed volume printed on the bag. Mixed concrete occupies less than the dry powder.
Bag sizeYield per bagBags per cubic yardApproximate dry weight
40 lb0.30 cu ft903,600 lb
50 lb0.375 cu ft723,600 lb
60 lb0.45 cu ft603,600 lb
80 lb0.60 cu ft453,600 lb

Block walls

Concrete block estimating rests on one number: 1.125 blocks per square foot of wall. Every standard US block shares an 8 by 16 inch nominal face, so that figure never changes — a 12 inch foundation wall takes exactly as many units as a 4 inch partition of the same size. What thickness changes is the weight of each unit and how much grout fills its cores.

Nominal is the word doing the work. An 8 inch block actually measures 7 5/8 by 7 5/8 by 15 5/8 inches, and the missing 3/8 inch on each face is the mortar joint. Add it back and the courses land on exact 8 inch increments, which is why wall heights in multiples of 8 inches avoid ripping a course lengthways.

Reinforcement is where estimating stops and engineering starts. Retaining walls, basement walls and most walls over about four feet need vertical bars in grouted cores, at a spacing set by the wall height, the backfill and your local code. Filling every core in 8 inch block takes roughly a cubic yard of grout per hundred blocks.

Curing is not drying

Concrete does not dry out to gain strength — it reacts with water, and the reaction needs that water to stay present. Concrete left to dry in the sun stops gaining strength early and stays weak, which is the single most common way a good mix ends up as a bad slab.

The schedule people actually need: foot traffic at 24 to 48 hours, cars at about seven days, and full design strength at 28 days. Keep the surface damp or covered for the first week, and longer in hot or windy weather.

Cold is the other risk. Below about 40°F the reaction slows sharply, and concrete that freezes before it sets is permanently damaged. Winter pours need heated blankets, an accelerator, or a delay.

Guides

  • How Many Concrete Blocks Do I Need?

    Count blocks for a wall from one number — 1.125 per square foot — then work out the mortar bags, the grout for filled cores and the courses you will end up with.

  • How Much Concrete Do I Need?

    Work out concrete in cubic yards from your slab dimensions, convert it to bags, and find the point where a ready-mix truck becomes cheaper than mixing it yourself.

Costs

  • Concrete Cost Per Yard in 2026

    What ready-mix concrete costs per cubic yard delivered, the fees that get added on top, and the point where bags stop being the cheaper option.

Common questions

How many cubic yards of concrete do I need for a 20 by 10 slab?

At four inches thick, about 2.47 cubic yards before waste, or roughly 2.7 with a ten percent allowance. That is 200 square feet times a third of a foot, which is 66.7 cubic feet, divided by 27.

How many bags of concrete are in a cubic yard?

Forty-five 80 lb bags, sixty 60 lb bags, or ninety 40 lb bags. Each figure is 27 cubic feet divided by the yield printed on the bag — 0.60, 0.45 and 0.30 cubic feet respectively.

How thick should a concrete slab be?

Four inches for patios, sheds and footpaths; five to six inches anywhere a vehicle runs, including garage floors and driveways. Thickening the edge of the slab is usually more effective than thickening the whole thing, and a properly compacted sub-base does more for durability than any extra inch of concrete.

How many concrete blocks do I need per square foot?

Exactly 1.125, and it does not vary with block thickness. Multiply the wall area in square feet by 1.125, subtract the openings, then add about five percent for cutting and breakage.

When can I drive on new concrete?

About seven days for a car, and 28 days before it reaches full design strength for heavy vehicles. Foot traffic is fine at 24 to 48 hours. Keeping the surface damp through the first week matters more to the final strength than anything else you can do after the pour.

Reviewed by Quban, Construction estimator, on . How these numbers are checked.